Baxter Residents Face New Assessment Decisions as Fairview Road Project Advances
Baxter’s proposed Fairview Road extension to Excelsior Road is moving through the improvement-hearing process, putting preliminary property assessments and a hardship-deferral deadline in focus for affected owners.
The project is not an approved construction contract, and the listed assessments are not final bills. A feasibility report prepared for the City of Baxter proposes extending Fairview Road through the Fruth property to the existing Excelsior Road roundabout near TH 371, with roadway, utility and trail improvements.
Project moves toward hearings
The project schedule lists the Baxter City Council’s July 21, 2026 action as receipt of the revised feasibility report and approval of a resolution calling an improvement hearing. The schedule also includes additional improvement, assessment, design, bidding and council steps before construction could begin.
The schedule targets construction in 2027, but it says the dates are subject to change. Construction would remain contingent on later council action, updated project costs and acceptable bids.
The city had already approved up to $130,500 for Widseth professional design and bidding-related engineering services at its March 17, 2026 meeting. That work supports the project’s current planning phase; it does not itself authorize construction.
Road, utilities and trail proposed
The proposal would build an urban curb-and-gutter roadway connecting the existing rural section of Fairview Road to the Excelsior Road roundabout. It also includes sanitary sewer, water, storm sewer and a 10-foot bituminous, nonmotorized multi-use trail.
The proposed layout includes modifications to the First Baptist Church of Brainerd parking lot and removal of an existing structure on the Fruth property if the project advances as designed. Two future entrances are proposed for each adjacent property. A separate access road would connect Fairview Road to Frandsen Bank and Trust if the median opening on Excelsior Road is closed.
The report also proposes utility stubs into the Fruth property to accommodate future development. That development has not been completed. Additional right-of-way and easements from the Fruth property would be needed, and the feasibility report assumes they would be dedicated to the city during future development and platting. No property-acquisition costs were included in the estimate.
Preliminary costs and assessments
The feasibility report estimates the total project cost at $2,198,835. It identifies $1,669,460, or 75.9%, as assessable project costs and $529,375, or 24.1%, as initial estimated city costs.
The estimated assessments include $136,375 for First Baptist Church of Brainerd parcels and $1,464,750 for Fruth properties. The Fruth figure includes held intersection-control assessments. Another $68,335 in held intersection-control assessments is listed for remaining properties in the applicable service area.
Those amounts are feasibility-stage estimates, not final charges to every Baxter property owner. The report says costs were calculated in 2024 dollars and may change because of design decisions, economic conditions, contractor availability and bidding. Actual costs would be determined through bidding and subsequent council action.
The report also recommends that the city review the assessment methodology and cost allocations to confirm that they comply with city policy and fairly assign costs to benefited properties.
Payment terms and hardship deferrals
The report says assessments generally would be collected in equal annual installments over five to 12 years. Developer-requested assessments for the Fruth property are identified for up to five years, while other properties are identified for 12 years. Interest would begin accruing when the council adopts the assessment, with the rate set after the city issues project bonds.
Baxter’s 2026 supplemental hardship-deferral form applies to applications for senior citizens, disabled persons and active military members. The form requires applicants to meet specified income, assessment-payment and property-value conditions. It also requires supporting documentation, a $50 application fee and, when applicable, proof of age, military orders or qualifying permanent and total disability.
The form says supplemental information must be returned by August 31, 2026. An approved deferral must be renewed annually by August 31, and deferred assessments continue to accrue interest until paid. The form does not automatically defer an assessment or eliminate the underlying charge.
For Baxter property owners, the next important steps are the improvement hearing, later assessment proceedings and council review of final plans, bids and project costs. The current proposal would add a road connection and trail while extending or modifying utility infrastructure, but the project, right-of-way arrangements and parcel-specific assessments remain subject to further municipal action.
Sources
- Baxter Fairview Road feasibility report and project schedule
- City of Baxter 2026 hardship-deferral form
- Baxter City Council March 17, 2026 meeting record
- Brainerd Dispatch report on the Fairview Road proposal