Redlands approves $97,888 City Hall skylight amendment
The Redlands City Council approved a $97,888 amendment to McKernan Inc.โs skylight-repair agreement for the future City Hall on Nov. 17, raising the contract from $583,105 to $680,993. Community Forward Redlands reported that the vote was unanimous. The agenda also called for an additional $97,888 appropriation to the Safety/City Hall Fund for the work.
The work is at the future City Hall, 300 E. State St., near the future City Council chambers. It replaces deteriorated skylight glazing and flashing. Staff said further inspection found deterioration and organic growth after the original plan called for cleaning the existing glass.
How the amendment fits the project budget
Does the amendment increase the renovationโs overall budget? The city told Community Forward Redlands that the added work would be paid for with previously approved contingency funding and would not increase the overall project budget. The skylight contract itself rises by $97,888; the cityโs explanation concerns how that added work is funded.
The original contingency was $1,402,941. By November, $345,483โabout 24.6%โhad been approved for spending, leaving approximately $1.06 million not yet approved. The renovation was reported 68% complete at the same time. That progress figure measures construction, not the share of contingency approved for spending.
The reported expected cost for the overall project was about $16.8 million, compared with the approximately $11 million design-and-construction estimate from September 2023. The difference is approximately $5.8 million, or roughly 53% above the earlier estimate. Both figures exclude the separate $16 million property purchase.
Council Member Paul Barich questioned whether further unexpected expenses could arise and raised concerns about project estimates increasing. Staff said renovation work can uncover conditions that were not apparent during initial planning and that a 10% contingency was included for unexpected work.
Sources
- Redlands City Council agenda, Nov. 17, 2026, City of Redlands / AgendaLink
- Redlands City Hall renovation costs draw scrutiny as project reaches 68% completion, Community Forward Redlands
- www.communityforwardredlands.com
Ask Interactive NewsLook for updates to this storyFind out what has changed since this story was published.
Discover more from Interactive News
Subscribe to get the latest posts sent to your email.