Mission updates Johnson Drive reconstruction and traffic-signal work
Mission reported July 10 that reconstruction of Johnson Drive between Lamar Avenue and Metcalf Avenue was underway, putting work on one of the city’s main east-west routes into an active construction phase.
The project affects a corridor used by residents, commuters and local businesses for daily travel and access. As construction progresses, people who travel through the area may need to account for changing traffic patterns, access conditions and pedestrian movement near the work zone.
Reconstruction timeline
Mission’s project information said construction was anticipated to begin in March 2026. The city estimates the reconstruction will be completed within about 270 days from the notice to proceed.
The 270-day estimate is measured from the notice to proceed, not from the date of the July 10 update. That distinction means the estimate provides a project window rather than a specific completion day. The city’s update did not give an exact completion date or a current percentage of work completed.
The project segment runs from Lamar Avenue on the west to Metcalf Avenue on the east. Johnson Drive is a primary east-west connection in Mission, so work in this section has practical implications for people reaching homes, businesses and other destinations along or near the corridor.
Separate traffic-signal project
Mission is also continuing a separate effort to enhance traffic signals along the Johnson Drive corridor. The city received Carbon Reduction Program grant funding for that work in partnership with the Mid-America Regional Council.
The signal improvements and the road reconstruction are related because they involve the same transportation corridor, but they are separate projects. The ongoing signal work does not change the reconstruction’s estimated 270-day duration.
For residents, commuters and business operators, the two projects mean that conditions along Johnson Drive may change as work advances. Traffic-control arrangements can affect route choices, travel times, property access and pedestrian safety, particularly near active construction areas.
Mission has not published a final traffic-control map or an exact schedule for individual traffic changes in the update. The city’s construction updates provide the place to check for current project information as the reconstruction and signal enhancements continue.
The immediate development is that the Lamar-to-Metcalf reconstruction has moved from planning into construction, while the separately funded signal project remains in progress. The 270-day estimate gives the public a broad planning window, but day-to-day travel effects will depend on how the work proceeds and how traffic is managed along Johnson Drive.