SCE extends Eaton Fire claims deadline, short of Altadena request
Southern California Edison has extended the deadline to submit claims to its voluntary Eaton Fire compensation program from Nov. 30 to Dec. 31, 2026. SCE announced the one-time extension on Nov. 24, giving eligible claimants about a month more to file.
The Altadena Town Council had sought an extension through the end of January, so the new deadline falls short of its request. SCE said it acted after requests from community members and leaders. The council chair welcomed the extension while urging SCE to keep monitoring whether more time was needed. Council member Morgan Whirledge said one additional month was insufficient; the responses were not uniform.
Who can file and what the deadline means
The program covers eligible homeowners, renters and businesses directly affected by the Eaton Fire. It includes certain claims involving smoke, soot or ash damage, as well as qualifying injury or death claims. Pasadena and Altadena residents are among those affected, but living in either community alone does not establish eligibility; claims must meet the programโs direct-impact criteria.
Dec. 31 is the deadline to submit a claim, not to accept a settlement offer. SCE says submitting a claim, receiving an offer or evaluating one does not waive litigation rights. Accepting an offer and signing a settlement agreement relinquishes claims covered by that agreement.
Claims, offers and payments are different measures
As of the morning of Nov. 24, more than 6,300 claims had been submitted, representing more than 19,000 individuals, trusts and legal entities, according to local reporting citing SCE. The company reported these offer and payment figures:
| Measure | Reported total |
|---|---|
| Offers | More than 3,500, totaling about $1.2 billion, to more than 8,700 claimants |
| Payments | About $700 million paid to nearly 5,000 claimants |
SCE said more than 80% of offers had been accepted and about 2% declined. Claims, people and entities represented, offers, and paid claimants are different measures; they do not establish that one group moved through identical stages.
SCE reported an average of about 36 days to make an offer after a claim is substantially complete. It said payments are made within 30 days after settlement conditions are satisfied. Those periods cover steps after filing, not the Dec. 31 submission cutoff. SCE said it would offer additional opportunities in December to answer questions and help people submit claims.
Sources
- SCE Extends Wildfire Recovery Compensation Program Claim Submission Deadline to Dec. 31, Edison International / Southern California Edison
- Altadena Town Council Asks Edison to Extend Eaton Fire Claims Deadline to End of January, Pasadena Now
- Southern California Edison Extends Deadline to Apply for Wildfire Compensation, Southern California News Group
- Edison Extends Eaton Fire Compensation Claims Deadline to Dec. 31, Pasadena Now
- Wildfire Recovery Compensation Program FAQ, Southern California Edison