Little Rock’s 30 Crossing Park Moves Into Final Design After $30 Million Bezos Grant
Little Rock has moved 30 Crossing Park from a grant announcement into final architectural design, but the downtown project is not yet fully funded or under construction.
On July 21, the Little Rock Board of Directors authorized the city manager to enter an agreement with Sasaki Associates Inc. to complete the park’s final architectural design. The city’s board communication says the design work will be paid with Bezos Earth Fund money held by the Little Rock Regional Chamber and reimbursed through the Chamber.
What the July 21 action approved
The city action allows Sasaki to continue work on the proposed park’s design. It does not identify a final contract value for this new design phase, and it does not approve construction of the full park.
The action builds on a $750,000 Sasaki contract authorized in 2024 for development of a master plan and Phase I design services for what was then also referred to as I-30 Crossing Park.
The measure includes an emergency clause and took effect after its passage on July 21. Its practical effect is to authorize the next design step while project partners work on the broader implementation plan.
A proposed downtown park near the River Market
The city’s July 7 announcement described 30 Crossing Park as an approximately 23-acre site in downtown Little Rock’s River Market district. The land was created through the Interstate 30 redesign and had previously included a cloverleaf exit-ramp area.
City plans describe a public-purpose park with green space, trails, arts and cultural destinations, sports, play, nature features and gathering areas. The project is intended to strengthen connections among downtown, the Arkansas River, nearby trails and other cultural destinations.
If completed as planned, the park could change how residents, visitors and workers move through the River Market area and could create new gathering and recreation opportunities for nearby businesses and community organizations. Those effects remain prospective because the final design and construction phases are still ahead.
The $30 million grant is not the full project budget
Little Rock announced the $30 million Bezos Earth Fund commitment on July 7. The grant is intended to support the project’s initial implementation and final design work, but it is smaller than the reported cost of the complete buildout.
Arkansas Business reported that a December 2025 estimate from Sasaki placed the overall project cost at $93 million to $128 million. The publication also reported a goal of using the grant to help attract another $60 million to $70 million in funding.
Those figures are estimates and fundraising targets, not final city appropriations or a guarantee that the entire project has been financed. The July 21 action specifically concerns final architectural design.
What happens next
Sasaki is expected to complete the final design while the city and its partners pursue additional financing for the larger park. Future construction decisions, funding commitments and approvals will determine whether and when the full buildout proceeds.
For Little Rock residents, the July 21 action is an implementation milestone: the Bezos commitment is now tied to an authorized design agreement. It is not a declaration that 30 Crossing Park is finished, fully funded or ready to open.