Los Lunas capital plan schedules major road, interchange, library and water projects for 2027-29
Los Lunas’ five-year infrastructure plan lays out a major pipeline of road, interchange, library, water, rail-park and transit projects scheduled primarily for 2028 and 2029.
The Village of Los Lunas’ FY2026-2030 Infrastructure Capital Improvement Plan, included in a June 11, 2026, capital-project agenda record, lists estimated project totals and anticipated project years. The plan provides a public roadmap for future infrastructure, but a listing does not by itself mean that construction is complete, fully financed or guaranteed to proceed on schedule.
Road and interchange projects
The Los Lunas West Loop is listed to begin in the 2028 project year, with a total estimated cost of $50.8 million. The plan also includes I-25 Highway 6 interchange enhancements in 2028, with an estimated total of approximately $7.52 million.
A separate North I-25 East and West Interchange project is scheduled in the plan for 2029, with a listed total of $101 million. That is the largest individual project total identified in the schedule.
Together, the roadway projects point to planned investment in major local and regional connections. The document identifies future project years and estimated totals rather than reporting completed construction or final contracts.
Water, library and rail-park investments
The plan lists a new water well No. 8 for 2028 at an estimated $1.45 million and a new water tank No. 8 at $900,000. Those projects are part of the village’s listed future water infrastructure work.
A new library construction project is also scheduled for 2028, with a listed total of approximately $18.84 million. The plan does not describe the library as completed; it identifies the project as part of the village’s capital pipeline.
Central Rail Park utility extensions are listed for 2028 at an estimated $7.6 million. The project would represent planned utility infrastructure for the rail-park area, subject to the future funding and implementation steps required for a scheduled capital project.
Transit access and next steps
Los Lunas transit-parking improvements are listed for 2028 at $1.8 million. Along with the road and interchange projects, the transit and utility entries show the range of infrastructure needs included in the village’s five-year plan.
The next known timing in the plan is the listed project-year schedule: several major projects are assigned to 2028, while the North I-25 East and West Interchange project is assigned to 2029. The capital plan identifies estimated totals and future-year timing, but it does not establish that every listed amount is secured cash or that every project will advance on the published schedule.
Sources
- Infrastructure Capital Improvement Plan FY 2026-2030, Village of Los Lunas
- Village of Los Lunas capital-project agenda record, Village of Los Lunas
Look for updates to this story