Nicollet Avenue reopens after 49 years as Kmart site awaits financing
Minneapolis reopened Nicollet Avenue between Lake Street and Cecil Newman Lane on Nov. 24, restoring a connection that had been closed since 1977. The 49-year interruption is over, though construction finishing work will continue into 2027.
The reopened segment restores a Nicollet Avenue route across the former Kmart-site block, connecting south Minneapolis toward downtown. The street is open to traffic; the adjacent redevelopment project has not begun construction.
A new bridge and wider sidewalks
The city rebuilt the street and replaced the bridge over the Midtown Greenway. The new bridge takes the place of a 1914 bridge built for streetcars. The project also added sidewalks up to 14.5 feet wide, a signalized midblock crossing, accessible ramps and off-street bicycle lanes on Cecil Newman Lane and West 29th Street.
Green stormwater infrastructure covers more than 15,000 square feet. The city also lists 35 new trees and more than 2,400 perennials and grasses, plus a Route 18 bus platform and shelter. Midtown Greenway users have a new accessible ramp from First Avenue South.
Street work is separate from Kmart-site plans
The street opening does not mean the former Kmart property is ready for redevelopment. The city describes that as a separate, 10-acre project: Trellis was selected to lead its first phase, but the team is still securing financing. Construction could begin as early as 2028; that is an earliest possibility, not a confirmed start date.
| Reported spending | What it covers |
|---|---|
| About $25 million | Nicollet Avenue reopening project, including $18.5 million for construction |
| $22.4 million | Earlier property acquisition and ending Kmartโs lease |
The two reported totals add to about $47.4 million, but they cover different expenses: the earlier property and lease costs are separate from the street project. The combined figure is not the construction cost alone.
Some work remains through 2027
Fencing, irrigation and planting are still underway. Work on Cecil Newman Lane between First and Nicollet avenues is scheduled to resume in spring 2027, and the new asphalt is scheduled for seal coating in July.
The city says community engagement from 2022 through 2025 helped shape the street design and site plan. Ward 8 Councilmember Soren Stevenson called the original closure a โgenerational mistake,โ CBS Minnesota reported.