Waitsfield wastewater project still faces cost hurdle before planned bidding
Waitsfield’s planned community wastewater project remains on a path toward a late-summer 2026 bidding phase, but the town must first bring the project’s cost after grants and subsidies below its approved $15 million bonding capacity.
A June 16 Planning Commission packet says the project cannot go out to bid until that threshold is met. That is a condition for moving forward with bidding, not a final construction award or guarantee that construction will begin in fall 2026.
Cost reductions affect the proposed system
The Planning Commission packet says project costs have continued to rise over the past two years. In response, the project team approved several cost-cutting measures, including removal of the sole proposed connection to Old County Road.
The Old County Road change is reported as a cost-reduction measure in the June 16 project update. It should not be treated as a permanent elimination from every future design unless a later final design or town decision confirms it.
The town’s project materials describe a municipal collection system intended to serve Irasville and Waitsfield Village. Treatment and in-ground disposal are planned at the town-owned Munn Site at the intersection of Kingsbury Road and Vermont Route 100. The town’s project overview lists an estimated gross cost of approximately $18.5 million and a planned treatment and disposal capacity of about 89,000 gallons per day.
Financing, easements and permits remain prerequisites
The June 19 project update listed June 30 as the target date for the Clean Water State Revolving Fund construction-loan application and Engineering Services Agreement Amendment 5. The document said the town was poised to submit the loan application before a June 30 deadline tied to a possible 50% subsidy and up to $1 million in principal forgiveness. The available record reviewed for this article does not establish that the application was completed.
The same update listed priority easement outreach for June and July, draft easements for July, state permitting reviews and completion of the 100% design in July. It said the project would become eligible for bidding once permitting approvals were in hand, final Vermont Department of Environmental Conservation approval was granted and the design reached 100%.
The town’s planned sequence called for bidding in late summer 2026 and construction to commence in fall 2026. Those remain planned milestones rather than a construction award or a guaranteed start date.
For affected property owners, the immediate issues may include user agreements and temporary or permanent easements covering conveyance lines, pump stations and individual property connections. The June 19 update said the town attorney was drafting easements and that town representatives planned site visits with owners along the conveyance route. It also said completed conveyance and pump-station easements would be required before execution of a construction contract.
Draft ordinance could shape future connection costs
Separately, the Waitsfield Water Commission has posted Draft Wastewater Ordinance Revision 5, dated June 16, 2026, and is inviting ideas, suggestions and corrections. The document is a proposal for future Selectboard consideration; it is not adopted law.
The draft establishes a proposed wastewater service area through an attached map and describes procedures for connection applications, capacity allocation, building-sewer and house-connection responsibilities, fees, user charges and enforcement. It also says that existing lawfully operating private wastewater systems within the proposed service area could continue operating, subject to the draft’s terms.
Under the proposal, the town’s wastewater board could establish user charges and fees through later resolutions. The draft says those charges could account for operations and maintenance, construction-related debt and allocated system capacity. It also contemplates connection fees for new connections, with specific schedules and amounts to be set through later board action if the ordinance is adopted.
For property owners, that means the practical questions are still developing: whether a parcel is inside the final service area, whether a connection is pursued, what easements are needed, how capacity is allocated and what fees or user charges are ultimately approved. The proposed map and connection details could change before final project and ordinance action.
What residents should watch next
Residents, businesses and landowners should watch for official updates on the construction-loan application, Engineering Services Agreement Amendment 5, final design and permit approvals, bid advertisements, easement contacts, the proposed service-area and connection map, and Selectboard action on the wastewater ordinance.
Waitsfield’s stated construction target remains fall 2026, but the project must first satisfy the net-cost threshold, complete financing and permitting steps, finalize design, secure required easements and successfully proceed through bidding.