Wilton’s Cannon Road Bridge project advances toward 2026 construction planning
Wilton’s Route 33/Cannon Road bridge replacement is advancing toward construction planning, with the Connecticut Department of Transportation identifying the project for 2026 work and the Town of Wilton reporting that design is approximately 90% complete.
The town’s March 13, 2026, capital-project update lists the project at an estimated cost of $6,574,540 and shows authorization to bid. It also estimates a construction start in 2026 and completion in 2028. Those milestones describe the current plan, not a completed project or a guarantee that construction will proceed on that schedule.
Bridge replacement over the Norwalk River
CTDOT identifies the project as 0161-0145 Wilton. The work would replace the Cannon Road bridge over the Norwalk River in Wilton. CTDOT’s project information anticipated construction beginning in spring 2026, subject to funding, right-of-way acquisition and permits.
The approved project information identifies June 12, 2026, as the relevant event date for the development. The town’s capital-project update provides the more detailed status report, including the design percentage, authorization to bid, estimated cost and projected construction timeline.
Cannon Road is a local transportation link. When construction eventually begins, the work will affect motorists and nearby residents, as well as emergency and commercial traffic using the crossing. The planned replacement is intended to improve the bridge’s long-term structural reliability and transportation resilience.
Public participation and remaining conditions
CTDOT’s project information includes a public-information meeting and says a public comment period follows that meeting. The approved records do not provide a closing date for the comment period.
The project’s progression to approximately 90% design and authorization to bid indicates that planning has moved beyond an early concept. However, the schedule still depends on conditions CTDOT identifies: funding, right-of-way acquisition and permits. The 2026 construction start and 2028 completion remain estimates until those requirements are satisfied.
For residents and people who use the Route 33/Cannon Road crossing, the immediate change is the project’s advancement through design and construction preparation. The approved packet does not establish that physical construction had begun by Aug. 7, 2026. It also does not establish a current bridge closure, traffic detour or full project funding.
The next known steps are the remaining approvals and preparations needed to move from the current design and bidding stage into construction. Until the required funding, property-related work and permits are in place, Wilton’s bridge replacement remains a planned project with an estimated 2026 start and 2028 finish.
Sources
- 0161-0145 Wilton, Connecticut Department of Transportation
- DPW Bonded and Grant Projects Update, Town of Wilton