Kansas City OKs first step toward $235M CPKC Stadium expansion and TIF
Kansas City MO—On July 2, 2026, the Council passed Ordinance No. 260565 to start talks on expanding CPKC Stadium, a TIF plan, and up to $235M in bonds.
Kansas City Council’s July 2, 2026 vote cleared a key procedural step for the Kansas City Current’s proposed CPKC Stadium expansion and related Berkley Riverfront-area redevelopment. The Council passed Ordinance No. 260565, which directs the City Manager to negotiate next-step documents, pursue a Tax Increment Financing (TIF) plan process, and sets the stage for special obligation bonds up to $235 million—subject to later approvals and feasibility review.
The approved action: a “framework” for negotiations and planning
Ordinance 260565 declares the City Council’s intent to support good-faith negotiations with the Kansas City Current over expanding the stadium and related riverfront-area project. It doesn’t finalize project terms or costs by itself. Instead, it directs the City Manager to pursue the next documents and decisions that would have to follow before any public financing is locked in.
Specifically, the ordinance directs the City Manager to:
- Negotiate and execute a term sheet related to the Project.
- Negotiate a comprehensive development agreement with Ballard Development LLC and/or its affiliates (in coordination with appropriate agencies and city incentive agencies).
- Support an application for a TIF Plan through the Kansas City TIF Commission.
- File with the Missouri Development Finance Board (MDFB) for state tax credit funding (through the State Tax Credit for Contribution Program), and—if approved—negotiate any related tax credit agreements.
- Explore other state economic development programs that may be available for the Project.
- Negotiate intergovernmental cooperative agreements with the State of Missouri and related agencies as needed.
- Enter a lease or exclusive license agreement for 50 years tied to levee improvements, including a framework for the levee promenade, Lydia pumpstation, and cafe zones.
- Ensure financial feasibility review happens first: the ordinance directs that the Director of Finance assess feasibility prior to executing agreements or seeking further approvals tied to bond issuance.
The project and geography: CPKC Stadium plus Berkley Riverfront Park elements
In the ordinance text, the “Project” includes an expanded CPKC Stadium along with a parking garage, mixed-use development, and supporting infrastructure in the Berkley Riverfront Park area.
The legislation also references specific Berkley Riverfront components tied to a lease or exclusive license agreement—language that includes levee promenade, Lydia pumpstation, and cafe zones.
The ordinance’s planning-scale cost framing is $1.4 billion.
The money question: TIF planning and a special-obligation bond ceiling of $235 million
Ordinance 260565 expresses support for a Tax Increment Financing Plan for the Project and directs the City Manager to pursue state incentive filings. It also sets up the possibility of public financing through special obligation bonds.
Here’s what the ordinance does—and doesn’t—say about the bond ceiling:
- The ordinance states the Council expects to facilitate issuance of special obligation bonds, in one or more series, totaling up to $235,000,000 to finance the Project.
- Before any agreements are executed or the city seeks further approval to issue bonds, the ordinance directs that the Director of Finance assess the Project’s financial feasibility.
In other words, the $235 million figure is a ceiling tied to future steps, not a finalized or guaranteed public-payoff amount today.
What happens next for residents and taxpayers
Because this was an early, framework-oriented action, the practical “watch list” for residents is the next set of documents and approvals that would give more clarity on timeline, scope, and cost-sharing.
Based on the ordinance directives and surrounding local coverage, the next milestones to look for include:
- Term sheet negotiations leading to a written term structure for the Project.
- A comprehensive development agreement covering stadium expansion, parking, mixed-use elements, and supporting infrastructure.
- TIF plan application materials to the Kansas City TIF Commission with more detail on eligible costs and the revenue capture approach.
- MDFB and state-incentive paperwork tied to the filings described in the ordinance.
- Financial feasibility analysis tied to whether additional bond steps can move forward.
- More public detail on traffic, parking, and infrastructure, including planning needed to address concerns raised around the vote.
Spectrum Local News reported that committee discussion included concerns about taxpayer financial risk, city credit and debt capacity, long-term parking infrastructure costs, diversion of revenue from other city priorities, and traffic/parking impacts in adjacent areas including Columbus Park and Union Hill. The reporting also said the finance committee added a requirement for more detailed planning, financial analysis, and transparency before final approval.
Community reaction: improvements welcomed, bond concerns persist
Coverage the week of the vote reflected mixed reactions. KCTV5 reported that some residents near the Berkley Riverfront said the expansion feels like a natural progression for the area, while also noting that the public financing element was a sticking point for some fans. KCTV5 also reported city staff were reviewing parking and traffic concerns as the process moved forward.
What to watch in the coming weeks
- Whether the city releases or updates the term sheet approach and the path to a development agreement.
- What gets submitted for formal TIF consideration (and what it says about eligible costs and revenue capture mechanics).
- Any published summary of financial feasibility work tied to the bond framework.
- Any next council votes that would authorize additional bond steps—and the documents that would support them.
Sources
- Kansas City Legistar: Ordinance No. 260565 (text)
- Spectrum Local News: committee concerns before the vote
- KCTV5: neighbors/fans reaction near the vote