Abilene S10B workzone starts July 13 near C.W. Gill Park: detours, parking
Abilene TX โ The City says Workzone Project S10B near C.W. Gill Park starts Monday, July 13, with construction expected to last about six months and parking limits.
Abilene residents driving near C.W. Gill Park should expect detours and street access changes starting Monday, July 13, 2026, as the City begins Workzone Project S10B.
The City says construction is expected to last about six months (weather permitting), and it asks drivers to watch posted signs and avoid street parking while work is underway. Vehicles may be towed if not relocated as needed.
What to know right now
- Start: Monday, July 13, 2026
- Timeline: about six months (weather permitting)
- Detours/signs: follow all detours and posted signage in the work area
- Parking: avoid parking in the street during construction
- Towing: vehicles may be subject to towing if not relocated as needed
Where the work is happening
Workzone Project S10B includes street work on roads bounded by S. 11th St. to S. 14th St. between Willis St. and Barrow St.
The Cityโs contract scope also covers activities such as removal and replacement of existing pavement sections, cement stabilization, concrete pavement work, repairs to curb and gutter, and installation of valley gutters.
Because construction is done in phases, the specific access and lane conditions can change. Drivers should rely on on-site detour routing and posted signage as the project progresses.
Detours, safety, and parking/towing warning
The Cityโs notice specifically asks drivers to follow all detours and posted signage and to use caution while traveling through the area.
It also asks residents and visitors to avoid parking in the street during construction. The City warns that vehicles may be towed if they arenโt relocated as needed.
How to keep up as conditions change
For the most up-to-date status and related work-zone tracking, check the Cityโs Street Projects page, which lists Workzone S10B in the C W Gill Park Area.
The Cityโs Street Maintenance Fund project listing also references S10B in the C W Gill Park Area and indicates it was previously postponed for utility improvements. Even with that context, crews may still adjust phasingโso itโs important to watch the posted signs in the work zone and re-check the City tracker as the project moves.
Sources