Evanston asphalt-pavement project carries Aug. 21 completion deadline
Evanston’s public-works asphalt-pavement improvements project is under a contract requiring completion by Aug. 21, 2026. The deadline gives residents and commuters a specific point for judging whether the work is completed on time, although the city records located do not identify the project’s current completion status or the streets affected.
The contract provides for liquidated damages of $1,000 for each consecutive calendar day after the deadline until completion and acceptance if the contractor experiences a qualifying delay. The amount does not represent a fine already owed, and the provision does not apply when an authorized change order extends or otherwise changes the contract requirements.
The City of Evanston published the bid record March 5, 2026, with bids due March 26. City Council agenda and contract materials dated April 7 repeat the Aug. 21 completion date and include contract-performance and payment provisions. The records also state that the project is governed by Wyoming public-works and resident-preference provisions.
The located materials do not identify the contractor, final contract price or a completion percentage. They also contain no final-acceptance record or delay notice. The next known milestone is the Aug. 21 completion deadline.
Sources
- 2026 City of Evanston Asphalt Pavement Improvements, City of Evanston, Wyoming
- City Council agenda and contract materials, City of Evanston, Wyoming
Look for updates to this story
Discover more from Interactive News
Subscribe to get the latest posts sent to your email.