Matthews board approves $1.568M Sam Newell path contract
Matthews commissioners approved a $1,568,204 construction contract for the Sam Newell Road Multi-Use Path on Nov. 23, 2026, according to MyTownViewโs meeting summary. The contract is with Carolina Cajun Concrete.
The Townโs meeting packet identifies the company as the lowest responsible, responsive bidder and recommends authorizing the Town Manager to sign. The memo does not say whether the contract has been signed.
The planned path is 0.64 miles from Williams Road to Crown Point Elementary School and is part of the Carolina Thread Trail. Town staff said there is no designated pedestrian connection to the school. They described the path, together with the Irvins Creek Greenway, as intended to create safer connections from nearby neighborhoods. That is the Townโs stated goal, not a measured safety outcome.
Funding and bid timeline
The Town describes an 80% federal and 20% local funding match. Matthewsโ share is $313,640.80, and applying the 80% share to the contract amount gives a federal share of $1,254,563.20. The Town says project funds were approved in its FY2027 budget and five-year capital improvement plan.
The North Carolina Department of Transportation authorized construction on Aug. 5, 2026. The Town received nine bids at a public opening on Sept. 23. Carolina Cajun Concreteโs $1,568,204 amount was $28,222.40 below the next-lowest listed bid, $1,596,426.40 from Hux Contracting.
The Town memo gives no construction start, completion or path-opening date. NCDOTโs construction authorization is not a schedule for when work will begin.
Sources
- Matthews, NC Meetings in 2026: Minutes & Summaries, MyTownView
- Board of Commissioners Packet, November 23, 2026, Town of Matthews
Ask Interactive NewsLook for updates to this storyFind out what has changed since this story was published.
Discover more from Interactive News
Subscribe to get the latest posts sent to your email.