Pittsford Schools Advance $48.7 Million Tax-Neutral Capital Project; Construction Continues Into 2026-27
Construction and facility improvements are continuing across Pittsford Central School District after residents approved a $48.7 million capital project described by the district as tax-neutral.
Voters approved the project on March 5, 2026, by a vote of 751 to 121. The referendum drew 872 total voters. The work is intended to address building-condition, repair, upgrade and modernization needs across district facilities, while construction continues into the 2026-27 school year.
Work underway at Pittsford schools
The district’s August update reports that new mental-health suites are progressing at Allen Creek Elementary School and Jefferson Road Elementary School. The update does not say that either suite is open or operational, so the spaces remain part of the ongoing construction work.
The transportation and maintenance facility’s fuel-tank project is nearing completion, according to the district. The update does not provide a project-wide completion percentage or a detailed construction calendar for 2026-27.
For students, families and staff, the work means that school facilities and operations will continue to be affected as projects advance. The approved project is focused on district infrastructure, rather than a new tax levy; the district’s description of the referendum as tax-neutral does not establish that taxes could never change under future conditions.
Transportation changes add a current safety focus
The district also has a new transportation director. The Board of Education appointed Jay Ballard at its July 14, 2026, meeting, with the appointment effective July 27.
Pittsford Schools is partnering with the Monroe County School Bus Safety Program and BusPatrol on stop-arm enforcement technology. The approved information identifies the partnership and technology effort, but does not specify the enforcement process or say that BusPatrol issues citations.
That transportation work gives families a current practical issue to follow alongside the construction: how the district and its partners will use the technology to address safety around stopped school buses.
Next major milestone
The district’s larger 2023 capital work includes an addition at Mendon High School. The addition is targeted to open in January 2027, providing the next dated milestone identified in the district’s updates.
As work continues, the district has reported specific progress at Allen Creek, Jefferson Road and the transportation and maintenance facility, but has not published a single completion estimate for the full $48.7 million project.
Sources
- Superintendent’s eNewsletters — August 2026, Pittsford Central School District
- Capital Project 2026, Pittsford Central School District
Look for updates to this story