Tampa City Council approves Rays stadium deal; Hillsborough County vote is next
Tampa City Council approved a revised agreement for a proposed Tampa Bay Rays ballpark and mixed-use district Thursday, August 27, but the project still depends on Hillsborough County commissioners.
The council voted 4-3 to advance the deal after an eight-hour meeting. Hillsborough County scheduled a special meeting for 9 a.m. Friday, August 28, to consider the Raysโ definitive documents. As of Friday morning, that county vote remained pending.
What Tampa approved
Under the revised terms, Tampa would make four annual infrastructure reimbursements of $20 million each. The payments would be limited to completed improvements in the proposed stadium district and would not be upfront payments to the Rays.
The city would be repaid, with interest, from future property-tax growth generated by the mixed-use development. That repayment mechanism depends on the district being built, generating taxable value and meeting the agreementโs implementation requirements.
The revised structure differs from an earlier proposal that called for $80 million from Tampaโs Community Investment Tax and $100 million from the cityโs Community Redevelopment Agency.
Proposed ballpark would reshape Dale Mabry campus
The proposed $2.3 billion to $2.36 billion project would be built on a 115-acre portion of Hillsborough Collegeโs Dale Mabry campus in Tampa. A privately funded mixed-use development would surround the ballpark under a proposed 35-year lease.
Plans described in the reported agreement include residences, retail, businesses, a major hotel and a reimagined Hillsborough College campus. The projectโs build-out, tax generation and infrastructure schedule remain dependent on future approvals and implementation.
If the county approves the documents, the parties could move toward bond validation, temporary classrooms and lot grading intended to help accommodate campus disruption during construction. Those steps are not guaranteed unless the county acts and the related documents take effect.
County decision carries the larger public commitment
Hillsborough County would own the proposed stadium and could contribute up to $796 million under the agreement. The reported package includes $360 million from the Community Investment Tax, $263 million in Tourist Development Tax-backed funding, $103 million from other county funds and $30 million in federal disaster-recovery money.
Combined city and county contributions would be capped at $876 million under the reported terms, while the Rays would provide more than $1.3 billion and cover cost overruns.
The countyโs special meeting is scheduled at the County Center with in-person and virtual participation. The countyโs official notice lists the meeting as 1 p.m. UTC, which corresponds to 9 a.m. Eastern time in Tampa. Until the commission votes and the documents are finalized, the stadium agreement should not be described as final.
What Tampa residents should watch
The project could affect roads, infrastructure, campus operations, nearby housing, businesses and future development around Dale Mabry Highway. The practical effects will depend on the final documents, construction schedule and pace of mixed-use development.
The community-benefits framework includes affordable housing, local hiring, minority- and women-owned business participation, small-business and workforce development, and youth programs. The reported materials do not specify a total spending amount for those commitments.
Residents and taxpayers should watch the countyโs vote, the final financing documents, the repayment terms, development milestones and enforcement of community-benefit commitments. Tampaโs approval advances the proposal, but Hillsborough County holds the immediate decision on whether it proceeds.
Sources
- City of Tampa council vote announcement
- Hillsborough County special-meeting notice
- WUSF financing and project report
Look for updates to this story