Buckeye approves data-center permit; construction still needs review
Buckeyeโs Planning and Zoning Commission voted 6โ1 on Nov. 24 to approve conditional-use permit PLZU-26-0012 for the proposed 157-acre Buckeye Energy Center, advancing the project to site-plan review. The vote does not approve a site plan, issue a building permit or authorize construction.
The site is about 4,700 feet west of the northwest corner of State Route 85 and Patterson Road in Buckeye. The proposal includes three data-center buildings, battery storage, diesel backup generators and an on-site natural-gas plant planned for up to 300 megawatts.
The applicant told the commission that Arizona Public Service could initially supply about 120 megawatts. Those figures describe different parts of the proposed power plan: the 300 megawatts is planned on-site generation capacity, while the APS figure is a potential supply estimate from the applicant, not a confirmed utility commitment.
Water, noise and emissions conditions
The permit includes 24 conditions. Cooling must be non-evaporative or hybrid, and a water-usage-effectiveness limit of 0.5 applies, excluding initial commissioning fill. Annual water-use reporting is also required. The projectโs actual water demand remains undetermined; the efficiency condition is not a total-use forecast.
The developer must submit a noise study with its site plan and analyze possible off-site temperature effects. Separate environmental permits would still apply to emissions from the proposed gas plant and backup generators.
Fire requirements and permit deadlines
City staff reported that the nearest Buckeye fire station is more than 20 miles from the site. The developer must reach a fire-infrastructure agreement within 12 months of approvalโby Nov. 24, 2027โor before its first building-permit application, whichever comes first. Battery storage also requires hazard-mitigation analysis, gas-plume modeling and an emergency-response and fire-safety plan approved by the fire marshal.
Two residents raised concerns at the hearing about groundwater, noise, heat, lighting, waste, nearby homes and the timing of public notice during Thanksgiving week. One asked the commission to delay its decision; the commission proceeded with the vote.
The permit sets Nov. 24, 2029, as the outside date for site-plan approval and Nov. 24, 2030, for a building permit. Those are approval deadlines, not promised construction or opening dates.