Providence order reaffirms data-center zoning restriction
Providence Mayor Brett P. Smileyโs Executive Order 2026-05 keeps the cityโs current zoning position on data centers in place while directing departments to develop a policy for possible future development. Signed Nov. 23 and effective immediately, it does not amend zoning or create a new prohibition.
The order says Providenceโs zoning ordinance does not list data centers as an allowable principal use and describes them as currently prohibited as a principal use citywide. Smiley called the action a โmoratoriumโ in spoken remarks, UpriseRI reported. The written order, however, reaffirms the existing restriction and assigns policy work; it does not impose a new zoning rule.
What the policy work covers
The Director of Planning is to work with the Sustainability Department, the Department of Inspection and Standards, the Fire Department and other relevant departments. They are to develop a comprehensive policy for future consideration, including whether and under what circumstances data centers should be permitted, potential scale limits, zoning and development standards, permitting and enforcement. The work is also to consider facility size, type and location and consistency with the cityโs Comprehensive Plan and Climate Justice Plan.
For purposes of the order, a data center is a facility used to store, process, manage and transmit digital data, including AI or cloud-computing services. The definition excludes wireless telecommunications facilities and data-processing activities accessory to another principal use when they occupy no more than 10% of that useโs gross floor area.
The policy is to consider possible effects on residents, electricity and water demand, municipal infrastructure, noise, air quality and greenhouse-gas emissions. Those are issues for review, not findings that particular harms have occurred in Providence. The order calls for opportunities for input, particularly from residents and communities likely to be directly affected.
The order recognizes the City Councilโs role in zoning and calls for Council-staff consideration of impacts and safeguards before a zoning change that would allow data centers. It also asks state officials to consider environmental and labor standards, utility demand, electric-infrastructure costs, protections for existing ratepayers and revenue sharing with both the State and host municipalities. Those requests do not establish protections or guarantee payments.
The order sets no deadline for completing the policy. UpriseRI reported that no data-center zoning hearing or vote had been scheduled as of Nov. 24. The order does not approve or decide the status of any particular project.
Sources
- Executive Order 2026-05: Addressing the Environmental, Infrastructure, and Community Impacts of Data Center Development, City of Providence
- Mayor Smiley Signs Executive Order to Address Environmental and Community Impacts of Data Center Development, City of Providence
- Providence Order Keeps Data Centers Out Under Current Zoning, UpriseRI
- Smiley orders city to develop data center policies, Providence Business News
Ask Interactive NewsLook for updates to this storyFind out what has changed since this story was published.
Discover more from Interactive News
Subscribe to get the latest posts sent to your email.