Greenville airport project to more than double SSC ramp space
Special Services Corporation broke ground Nov. 19, 2026, on a new fixed-base-operator facility at Greenville Downtown Airport, with planned ramp space more than twice SSCโs existing area. The comparison is with SSCโs ramp space, not the airportโs overall capacity, WSPA reported.
WSPA reported plans for nearly 24,000 square feet of hangar space, 13,000 square feet of office and amenity space, and 5,000 square feet of storage. Planned services include extended fueling hours, a pilot lounge, an exercise room and day rooms for travelers; these additions are not yet operational.
The current reportโs nearly 24,000-square-foot hangar is close to the 23,873 square feet in an earlier SSC plan announced in November 2024. That plan listed more than 6,800 square feet of office and assembly areas, compared with 13,000 square feet of office and amenity space in the current report. Because the categories differ, the figures do not establish a specific design change. Airport director James Stephens told FOX Carolina the airport had not grown at the same pace as the surrounding community; that is his assessment. The groundbreaking marked the start of the project.
Sources
- New facility aims to meet growing demand at Greenville airport, WSPA 7NEWS, syndicated on AOL
- Greenville company to break ground on Downtown Airport expansion, FOX Carolina
- SSC Marks One-Year Anniversary of Hangar Fire and Outlines Plans for New Facility, Special Services Corporation
Ask Interactive NewsLook for updates to this storyFind out what has changed since this story was published.